Access Floor Specification  


RAISED ACCESS FLOORS

250            ENVIRONMENTAL CONDITIONS

      Areas for storage and installation must be clean, dry, ventilated and free from both excessive or rapid variations of temperature and humidity. 

      Subfloor temperatures must be maintained above 5C.

 

280            DUSTPROOFING

      Ensure that surfaces to be sealed are clean, dry and free from dust, grease and other contaminants.

      Apply two coats of tinted sealer, recommended by the raised access floor manufacturer, to all concrete and masonry surfaces within the floor void to prevent dusting throughout the life of the installation.

 

310            WORKMANSHIP GENERALLY

      Store and install floor components in dry, well ventilated conditions not subject to extremes of temperature of humidity.

      Ensure that the subfloor is clean before installation commences and that cleanliness is maintained throughout the installation.

      Install the floor, accessories, finishes, etc., to achieve specified levels of performance.

      The completed installation to be level, stable, firm and free from bounce, squeaks, vibration and lipping between panels.

      Adequately protect from dirt, stains, damage and overloading until Practical Completion.

 

320            PEDESTAL STRUCTURE AND FIXING TESTS

      Test pedestals to MOB PF2 PS/SPU, test T42.00 to prove the need or otherwise for mechanically fixing to the subfloor and for site quality control.   Tests to be carried out in the presence of the CA.

      Where an adhesive fixing fails as a result of subfloor failure, arrange for the Main Contractor to make good the subfloor.   Re-fix using mechanical fixings and re-test.

      If any pedestal structure fails, replace the pedestal and re-test.

 

330            SETTING OUT

      Where not shown otherwise, set out floor system to ensure that cut panels are not less than half in width, particularly at doorways, thresholds, etc.

 

340            SEALING OF CUT PANELS

        Seal all exposed cut edges of panels which incorporate moisture sensitive or combustible cores with Class 0 rated aluminium foil self-adhesive tape.

 

350            PERIMETERS

      Ensure that the installed system has sufficient lateral stability to enable it to be independent of abutting elements.

      Provide a 10mm expansion gap at all abutments and fill with a resilient closed cell filler before fixing skirtings, cover strips, etc.

 

360            CAVITY BARRIERS

      Material:  PVC sleeved mineral wool.

Fire resistance to BS 476 Part 20.

Integrity / insulation (minutes):  30 minutes.

      Unless shown otherwise, install barriers to subdivide floor void into areas not exceeding 20m square.

      Fix securely to subfloor, at joints and as necessary to ensure permanent stability and continuity with no gaps, to provide an effective barrier to smoke and flame.

      Seal any gaps at junctions of cavity barriers with floor panels, walls, ducts, pipes, cable trays, etc., with mineral wool or other suitable material to prevent penetration of smoke and flame.

      Access panels above cavity barriers to be screwed down or otherwise firmly secured.

 

390            ELECTRICAL CONTINUITY AND EARTH BONDING

      All substantial metal parts of the floor to be electrically continuous and fully earth bonded in accordance with BS 7671 (The IEE Wiring Regulations).

      Liaise with the electrical subcontractor to agree the number and location of earth bonding connection points.   Supply connectors as necessary for use by the electrical subcontractor.

 

400            TESTING ELECTRICAL RESISTANCE

      Arrange for a qualified electrician to test the floor to verify compliance with MOB PF2/SPU, clause P9.01.   Notify the CA to enable him to witness the testing.   Submit a test report to the CA.

 

410            PROTECTION

      Ensure that no part of the floor installation is:

      Used as a platform for storage of equipment and materials.

      Subjected to static or dynamic loads which exceed those for which it is designed.   Adequate precautions, including the use of spreader plates, must be taken during installation of equipment and any work on other elements e.g:  ceilings.

      Walked on within 48 hours following the use of adhesives to fix pedestals to the subfloor.

      Left unprotected prior to Practical Completion.

 

420            PANEL LIFTING DEVICES

      Provide Main Contractor with two sets of lifting devices suitable for each of the floor finishes installed.   One set to be for the use of subcontractors requiring access to the void and the other for handing over to the CA at Practical Completion.

 

430      USER INSTRUCTIONS      

      Provide the Main Contractor with two copies of the floor manufacturer's maintenance and user instructions.   One copy to be for the use of subcontractors requiring access to the void and the other for handing over to the CA at Practical Completion.   The contents of the instructions to include:

      The correct method for lifting and replacing panels including limitations on the sequence and number of panels which can be removed at one time.

      The permissible loadings that can be applied to the floor, with guidance on the use of spreader plates, etc., during the installation of equipment and subsequent maintenance.

      Methods for installing cabling, ducts, etc., so as to prevent damage to the supporting structure.

      Cleaning methods for the panels and any integral finish(es).

 

450            POST INSTALLATION VISIT

      After completion of services and other associated work:

      Thoroughly inspect the floor installation for defects.   Prepare a schedule of outstanding defects and submit a copy to the CA.

  Copyright annor Ltd   2004